Skip to main content

2025

Global Power Transmission Report

Regional Market Overviews

Spain

Spain has experienced the most rapid growth in renewable energy penetration among European Union countries in recent years. Progressively, conventional energy resources are being phased out, as wind and solar power generation occupy the predominant place in the energy mix. The speed of this shift, however, outpaced the transmission network expansion. The rising instances of curtailment point to the constraints imposed by an inadequate grid capacity. Closing this gap would require time. The rise in investments in the last couple of years is encouraging, but the operator and the policy authorities must do more to meet the requirements ahead.

GDP (Current Prices) USD (2023)

1,621 Bn

Projected Average GDP Growth (2024-2028)

2.0%

10-year Govt Bond Yield (12-month rolling average)

3.2%

Country Credit Rating

A

Renewable Energy Share

41%

Total Transmission Line Length (Km)

48,633

GDP Source: IMF, World Economic Outlook

Transmission Network

The Spanish power transmission network, operated by Red Eléctrica de España (REE), is predominantly at 220kV and above voltage levels. Over recent years, the network has stood out in the European Union for its progress in achieving a decarbonised power system. Seamless grid integration is among the key challenges for the TSO, not least because of the increased prevalence of renewable power. The country’s geography requires that it have ten different electrical systems. The non-peninsular areas have separate operations because of their size and isolation. (REE, 2024).

The peninsular system is connected to France, Portugal, Andorra and Morocco, accounting for over 90% of the total power demand. The peninsular segment is notable for its cross-border interconnections, which enable cross-border power trade. The Iberian power market, involving integrated Portuguese and Spanish power systems, plays an important role in this regard. The interconnection is gradually being augmented even further for enhanced transactions. Due to the critical role of these projects, several of Red Eléctrica’s interconnection projects are also classified as ‘projects of interest’ in the EU, which helps attract funding and related support.

The onshore transmission infrastructure is expanding to accommodate demand arising from new connection requests, reinforcement of links between the islands, and improving the network’s meshing and reliability. By the end of 2023, the operator added 157 km of new lines and 143 new substations (REE, 2024). The capacity growth needs to be much higher to match the rising demand on the grid. Between 2019 and 2023, the total transmission line length registered a CAGR of 0.4%, while the year- on-year growth in 2023 was just about 0.2%. The line length grew by an annual average of 2.1% between 2010 and 2016. There has been a deceleration in the incremental capacities since then (Statista, 2024).

Transmission Line Length
Line Length (circuit km)
66 kV 3,075
132 kV 3,075
220 kV 20,273
400 kV 22,210
Total 48,633
Source: Red Eléctrica
Cross-border Transmission Linkage
Country Linkage TSO/Business Concern About the Linkage
Spain – France Inelfe (equal share of TSOs REE and RTE) A 64.5km long link commissioned in 2015 enabling 2,800MW in power transfer capacity. There are four HVDC lines in this interconnection. Another is due by 2027 (IEA, 2022).
Spain – Portugal REE and REN (Portugal) The existing link comprises six 400kV and three 220kV lines (ERSE, 2023)
Spain – Morocco REE and ONEE (Morocco) Two HVAC 400kV lines with a combined power transfer capacity of 1,400MW (MED, 2022)
Spain – Andorra REE and FEDA (Andorra) Existing interconnection is worth about 107MW and is due for reinforcement / expansion (European Parliament, 2023)
Source: Red Eléctrica, ERSE, IEA

Drivers in Energy Transition

The Spanish power system has been progressively operating with a rising share of renewable energy. Its ambitious renewable energy targets are well complemented by a steady capacity addition rate. Between 2021 and 2023, an annual average of 7.6GW of renewable energy generation capacity came online, which is more than thrice the average capacity added between 2017 and 2020 (IRENA, 2024). With policy and regulatory support, the renewable pipeline has grown manifold in recent years. As of July 2024, the Spanish government had approved the construction of over 28GW worth of renewable power projects. (Reuters, 2024). The country’s rapid progress in renewable energy stands out in the region – Spain was ranked among the top three countries for the rise in renewable energy penetration achieved between 2022 and 2023 (EEA, 2024).
Source: Energy Institute
The growth in clean energy resources is progressively outpacing the grid capacity. The rise in grid congestion and curtailment episodes coincides with the accelerated pace of capacity addition in wind and solar energy. Since 2022, congestion management costs and the volume of non-compensated renewable energy curtailment have risen sharply. Between 2017 and 2020, the cost of grid restriction was an annual average of €390 million. In 2022 and 2023, it reached €1.3 billion and €2.1 billion, respectively. Non-compensated curtailment is a more significant concern – in 2022, over 1TWh of renewable energy, amounting to 1.2% of the related generation asset output, was curtailed. Technical restrictions involving grid congestion are generally manageable through measures related to voltage control, reserves, and market operations. Non-compensated curtailed volumes are primarily due to an inadequate grid capacity. (Aurora, 2024).
Source: Energy Institute

An expanding renewable energy base increasingly displaces a significant share of conventional energy resources. Coal is the most discernible one in this regard. Its already insignificant share will decline further as the government actively seeks to allocate replacement capacities instead of coal plant retirements. (Energy Storage News, 2024). The entire process could be completed by 2025 as the speed of the process has been far higher than anticipated earlier. Active policy assistance regarding financial support for the plant operators, labour and other key stakeholders has helped. A much less steep decline is observed in the case of gas-based power, whose relative share stood at 22% in 2023 against 26% in 2020. The advantages of gas-based power units, such as enabling grid flexibility, have helped retain their share in the power system, although they have a diminishing role. According to the country’s gas grid operator Enagas, the gas-fired power plants are likely to be in operation beyond 2030 (Montel News, 2024).

The displacement of conventional energy sources extends to nuclear power, where a marked decline is underway. A significant share of nuclear generation is already going offline in the run to a targeted phaseout by 2035 (Reuters, 2023). In March 2024, the nuclear power generation in the grid was reduced to half, partly due to the recurring maintenance issues and in significant part due to the surge in renewable power. The power plant operators held high wind power output as the major reason for placing the units on standby (S&P Global, 2024). Officially, the decommissioning of nuclear power plants is expected to start in 2027, expecting renewable energy and energy storage capacities to compensate for the gap (Balkan Green Energy News, 2023).

The transmission operator is thus likely to face significant pressure from the displacement of conventional energy in the upcoming 5-6 years. Grid flexibility options such as in gas or long-duration battery storage may play an enhanced role. Notably, the large-scale phaseout of conventional energy does not impact the outlook for electricity demand. BNEF projections show that the country’s total electricity demand, modelled in a macroeconomic framework, could register a compound annual growth rate of 0.7% between 2024 and 2035. Instead, the sub- transmission (or the medium-to-low voltage distribution network) could be in focus because the same BNEF projections point to a 23% rise in demand arising from electric vehicles.

Policy Regulation

The policy and regulatory backdrop for power transmission is centred on the pace of the energy transition and the expansion of the infrastructure to support it. The latest renewable energy targets point to the ambitious scale. As of September 2024, the government approved 76GW of solar and 62GW of wind for commissioning by 2030 to achieve an 80% share of renewable energy in total power generation (PV Magazine, 2024). The Ukraine war and resulting energy crunch added impetus to the renewable energy goals, as regulatory norms were suitably amended to facilitate deployments.

Transmission plan approvals are vital to the grid infrastructure expansion process. In 2022, the government approved a four-year investment plan to augment and strengthen the grid. The plan amounted to about €7 billion in total spending, including sub-transmission networks and the high-voltage transmission network, the latter comprising 2,700 km of new lines and 700 km of new undersea interconnector links. Renewable energy connectivity is the highest priority in this plan, as it supports the national objectives in decarbonisation. (MITECO, 2022).

The government departments have also initiated long-term transmission planning for the 2025-2030 horizon, considering the project pipeline already in progress from the previous planning periods and the new proposals. Also, the planning process, especially the stage involving public hearings, is being modified to make it conducive for strategic projects.

In the meantime, other measures are being taken to streamline the rush for grid connectivity. Recent regulatory amendments stipulate an auction-based allocation approach to bring order to the existing process. This is being gradually brought into implementation. In April 2024, the Ministry for the Ecological Transition and the Demographic Challenge (MITECO) launched a capacity tender for synchronous generation from renewable and storage-based units. The tender aims to grant transmission access through pre-identified grid nodes at 220kV and 400kV (Enerdata, 2024). More such auctions can be expected as developers expand upon the generation pipeline. Furthermore, the regulations encourage converting existing generation units (especially renewables) into hybrid mode, i.e. generation with storage, without losing the original grid access rights.

A critical regulatory stipulation related to grid investment is presently under review. It refers to a legal cap on the investments of power transmission and distribution network operators. The investment limit for the power transmission network operator is 0.065% of the Gross Domestic Product. Considering the emerging investment requirements, this norm is overdue for revision. In January 2024, a government minister spoke about the ongoing deliberations to raise the limit (Reuters, 2024).

Market Opportunity

REE’s parent company, Reidia, has the latest quarterly financial results showing a rise in grid investments. According to the latest financial results, REE’s investment during April-September 2024 rose 18% (reaching €603 million) over the previous year’s comparable period. Strategically important projects under development include the interconnectors, and the 200MW Chira-Soria pumped hydropower project. (redeia, 2024). The TSO’s annual investments have almost doubled between 2019 and 2023.

Cross-border interconnector projects are among the critical focus areas in existing investment plans. About 18% of the transmission investment is exempt from the regulatory cap, and this is almost entirely made up of interconnector projects. Such investments are also important because Spain lags behind the EU’s target of maintaining interconnection capacity at a 15% share of the total installed generation capacity. Many projects are thus presently in the planning stages and may need a prioritised investment allocation.

The integrated Iberian energy market, comprising Spain and Portugal, may need additional investments to realise the net zero objectives. The existing investment plan, spanning the period of 2021-2026, provides for an outlay worth €7.3 billion. Over 80% of the planned spending is guided by interconnections, renewable power connectivity, and system reinforcements.

Estimated Transmission Grid Spend
Year Spend ($ billion, real 2023)
2024 1.8
2025 1.9
2026 1.9
Source: BNEF
Major Transmission Projects in Pipeline
Project Particulars Cost Planned Commissioning
Iberia- Mallorca A second 2x200MW link between the mainland and the Balearic Islands. $1.4 billion Around 2026
Tenerif- La Gomera Connecting the Canary Islands through 36 km long undersea cables. $0.1 billion 2025
Bay of Biscay (Spain- France) A 400km long HVDC link to raise existing power transfer capacity. $3.24 billion 2028
Aragon- Western Pyrenees and Navarra- Landes Two new projects between Spain and France presently in the planning and scoping stages
Source: BNEF

Outlook

The ongoing network investment under implementation refers to the approved plan period of 2021-2026. Fully implementing this plan would entail 2,681 km of new transmission lines and 7,057 km of uprated lines with related expansion in other transmission assets (Redeia, 2022). The trend so far points to much lower annual incremental capacity. In the five years to 2023, an average of 192 km of line length was added annually. Thus, the progress in this plan will be a vital input for investors and developers, and the subsequent transmission planning period of 2025-2030, for which studies are underway.

Better incentives are needed to address the issues of timely capacity augmentation. The cap on the grid operator’s investment commitment stands out as an oddity compared to expectations of large-scale infrastructure expansion. The planned revision of this cap is overdue, and delays are unlikely to help the operator’s case. Otherwise, the investment commitments are likely to lag the required levels. For instance, BNEF’s Net Zero Scenario projections suggest that Spain’s annual average investments in the grid network (transmission and distribution) should be $6.4 billion from 2024-2030. In practice, the annual planned investment till 2026 is at $4.7 billion.

Spain’s success in energy transition goals is likely to be tested by the timeliness of the grid network availability. The planned capacity addition will also entail a marked shift from the legacy processes followed by the regulator, policymakers and network operator over the years.