Skip to main content

2025

Global Power Transmission Report

Regional Market Overviews

The Netherlands

In recent years, the Netherlands’ power system registered among the highest renewable power generation capacity growth worldwide. The capacity addition is likely to be sustained, implying high pressure on the grid operator to meet connection requests on time. Additional demand from new sectors like Data Centres makes this phase increasingly challenging for the grid operator. Some of the recent concrete policy steps with the government indicated the importance being attached to resolve this issue. Expansion of the Dutch transmission system is also vital for the European region’s ambitious goals of tapping into the North Sea offshore wind power potential, by means of an energy hub. The progress in the network growth is, therefore, a lot more crucial than before.
GDP (Current Prices) USD (2023)

1,155 Bn

Projected Average GDP Growth (2024-2028)

1.5%

10-year Govt Bond Yield (12-month rolling average)

2.6%

Country Credit Rating

AAA

Renewable Energy Share

47%

Total Transmission Line Length (Km)

14,518

GDP Source: IMF, World Economic Outlook

Transmission Network

The Dutch high-voltage power transmission network operates at 220kV and 380kV voltage levels with a total line length of 14,518 circuit km (as of end-2023)(Power Technology, 2024). The grid operator, TenneT, is the sole entity for managing the power system. TenneT is also one of the four transmission system operators in the German power system. This might change in the near future, as discussions to divest the German operations have been going on for quite a while. TenneT’s Dutch business, the focus of the present discussion, is increasingly driven by the need for rapid network expansion, in addition to the incremental reinforcement requirements.

Renewable energy, and especially offshore wind energy, plays a central role in the region’s energy transition framework, as laid out in the European Commission’s long-term goals. For TenneT, this means getting the infrastructure ready for wind power projects in the North Sea. The interconnector lines are vital in this context. Its existing link with the UK, for instance, will be bolstered with the ongoing work on the LionLink hybrid interconnector planned for 2030. In the onshore grid segment, the expansion works are largely about augmenting capacities to meet the surge in grid connection requests. For the last 3-4 years, TenneT has been struggling to manage the spike in demand for new connections.

Grid reinforcement is being prioritised as a strategy to enhance capacities with relatively lower lead times. it is replacing 220 kV lines with 380 kV lines where possible. For example, in 2023, it completed a 40 km upgrade of the electricity highway between Eemshaven and Vierverlaten, boosting transport capacity. Additionally, TenneT is implementing the ‘Better Use of Existing 380 kV Programme’ (‘Beter Benutten’), which enhances the capacity of the current 380 kV transmission network by replacing old conductors with new ones and thus avoiding the time-consuming process of building new lines and alleviating congestion more efficiently (TenneT, 2024).

Notably, to address local community and household concerns, the underground transmission lines are being prioritised. This refers to TenneT’s network that operates at 50kV, 110kV and 150kV voltage levels. There is a government scheme to relocate such overhead lines in the populous areas, but with a rider that the local municipal authorities bear 15%-20% of the cost. This policy also states that if a new overhead high-voltage line is built, an existing line must be put underground to ensure the total length of overhead lines doesn’t increase (TenneT, 2022).

Cross-border Transmission Linkage
Country Linkage TSO About the Linkage
Netherlands – Denmark TenneT and Energinet (Denmark) Known as COBRAcable, with €600.0 million investment, 325 km long, 320Kv HVDC line with 700.0MW capacity, commissioned in 2019.
Netherlands – UK TenneT and National Grid (UK) Known as BritNed, with €600.0 million investment, 260 km long HVDC line with 1.0GW capacity, operational in 2011.
Netherlands – Norway TenneT and Statnett (Norway) Known as NorNed, with €600.0 million investment, 580 km long HVDC line with 700.0MW capacity, operational in 2008.
Source: TenneT

Drivers in Energy Transition

Of late, the Dutch power market had an exceptionally high capacity addition in its renewable power generation resources. Between 2018 and 2023, the installed renewable power capacity grew at a compound annual growth rate of 29% (IRENA, 2024). In 2023, about half of the EU’s new offshore wind power capacity was from the Netherlands’ capacity addition (EV Wind, 2024). The policy target of 70% sustainable power generation by 2030 (Netherlands Enterprise Agency, 2024) is primarily based on the offshore wind power potential. The project pipeline is thus rapidly expanding – in June 2024, the government awarded 4GW of offshore wind project contracts, and another 4GW tender is due in mid-2025 (S&P Global, 2024).
Source: Energy Institute
The outsized growth in demand for renewable power connectivity has stretched the grid limits. TenneT’s connection waiting list has risen exponentially. As of October 2024, the Dutch grid had 3.5GW of renewable power capacity in the queue, waiting for a connection (DCD, 2024). Total grid connection requests reached 19,000 in 2024, as compared to 7,000 in 2022. As a result, about nine out of ten provinces face some kind of restriction or suspension in new grid connections. Capacity expansion, the only way to address this, lies in the long-term i.e. around 2030, when the existing projects under development may partially close the gap (Aurora, 2024). The intervening period is likely to be subject to continued constraints. Grid management in such circumstances is likely to be more challenging, with conventional power generation resources rapidly taking a backseat.
Source: Energy Institute

The government has a legislated target of 2029 for phasing out coal-based power generation. This is despite the short-term measures of 2022 allowing an extension of some power plants (ABN Amro, 2024). The binding target helps add credibility to the policy goal of a carbon-neutral power sector by 2035. Unlike coal, gas-based power has a different premise. While the trend shows a gradual decline in the contribution, from 50% in 2018 to 37% in 2023, gas-fired power plants are important in the grid as a flexible generation resource. Grid-scale energy storage can potentially fill this gap but is constrained by technological limitations of short duration (2-4 hours). All the same, the direction of transition over the years makes it abundantly clear that renewable energy penetration is poised to displace fossil-based generation resources.

The Dutch power system is also facing a spike in demand. At the sub-transmission or distribution level, the emerging demand sector is for electric mobility. The rise in electric vehicle penetration and the emergence of large-scale battery manufacturing units to cater to vehicular requirements have added to the overall power demand. At higher voltage levels, the data centres constitute the most important segment for the grid operator. Amsterdam is a data centre hub in Europe. The Dutch Data Center Association projects the country’s IT capacity to grow at a CAGR of 9.7% from 2024 to 2029. This growth will increase the total data centre capacity from 863.0MW in 2024 to 1.4GW by 2029, nearly doubling in just five years (Dutch Data Center Association, 2024).

Policy Regulation

Being state-owned, TenneT’s business has a fair share of government involvement regarding the grid’s growth and its related key issues. The grid’s role in the energy transition objectives makes such involvement essential. One example is the Grid Congestion Action Plan, wherein grid operators (in transmission and distribution segments) work with the government to resolve the pressing issues of grid congestion and connection request queues. This includes measures such as faster approvals, speedy construction where feasible, better utilisation of existing infrastructure assets and engaging external parties to make some facilities (e.g. battery storage) available to others (TenneT, 2024).

Other areas of key policy support include TenneT’s grid capex and its financial wherewithal. The Dutch government, as a policy measure, has extended financial support for TenneT’s investment commitments. In June 2023, the government provided €1.6 billion for TenneT’s Dutch operations. In 2024, it provided a bridge loan facility of €25 billion, securing TenneT’s planned investments for 2024 and 2025 (TenneT, 2024). The funding assumes significance as TenneT struggles to find a buyer for its German power transmission business.

Source: Aurora Energy

Growth in the grid fees helps sustain the operator’s finances. The grid offtakers (distribution system operators) pay for the power transmission, construction and maintenance, and grid balancing services. Since 2022, grid fees have been rising in the Netherlands. Between 2022 and 2024, TenneT’s allowed revenues for the Dutch power system increased by three times. The rise in energy prices is the main reason (Aurora, 2024). The other key factor is the cost of offshore grid development, which is likely to exert upward pressure on the grid fees in the upcoming periods. Compared to its neighbouring countries, the Dutch grid fees are significantly higher. Alternative measures may be needed to ease the burden on the offtakers.

There are changes underway in the transmission tariff methodology to be brought into effect from 2025 for greater flexibility. Customers connected to the EHV grid will see an 8% reduction in costs, while those on the HV grid will experience a modest 0.4% increase. This shift is primarily due to the decline in electricity prices in 2023 (TenneT, 2024).

Market Opportunity

By the end of 2023, the grid operator’s total investment in the Dutch network reached €2.9 billion – almost three times its level in 2018 (TenneT, 2024). The momentum of expansion and reinforcement projects is likely to be sustained. TenneT’s investment plans for the Dutch grid involve about 700 projects (TenneT, 2024) covering five 380kV lines and modernisation of 140 high-voltage substations.

The long-term investment plan for the period 2024-2033 was circulated in April 2024 as part of the regulatory review process. Separate plans have been drawn for onshore and offshore, as the latter involves different regulations (TenneT, 2024). The operator anticipates €60 billion of investment and about 400km of new lines in the Dutch high-voltage transmission system by 2034 (Reuters, 2024). A final confirmation from the regulator would lend credence to the investment estimates. In the meantime, preparatory work is picking up. In August 2024, TenneT signed four-year deals worth €2.5 billion with civil construction companies to expand its overhead transmission lines in the Netherlands.

Some of the vital expansion projects are in the offshore grid segment. One ongoing project is the 2GW Nederwiek-2 offshore HVDC transmission system for commissioning by 2031. In June 2024, TenneT awarded €2 billion worth of construction and development contracts to the developers Seatrium and GE Vernova for the Nederwiek project (NS Energy, 2024). The latest contracts are in addition to the €3.8 billion worth of contracts earlier with NKT and Prysmian Group for cable connections involving Dutch offshore wind farms (NS Energy, 2023). TenneT is targeting an offshore transmission capacity of 40GW by 2030 to connect the Dutch and German North Sea wind power projects as part of the larger commitments by European countries to develop the North Sea wind power hub (PwC, 2023).

The planned LionLink interconnector project to link UK and Dutch grids contributes to the goal of an integrated North Sea grid. This project is also regarded as a multipurpose interconnector as it will connect the two power systems via a Dutch 2GW offshore wind farm, besides operating as a conventional interconnector for power trade. The project is scheduled for commissioning by 2030 (TenneT, 2024).

TenneT’s ongoing phase of accelerated investments is also marked by its adoption of technologies to enhance efficiency. Specific technology solutions are being deployed for better power transfer capacities. As of July 2024, the utility was using Dynamic Line Rating at its 380kV and 110kV-150kV connections, which enables up to 30% more transmission capacity within the existing infrastructure base. It is being rolled out on a rising number of connections to mitigate waiting times without jeopardising reliability levels (DCD, 2024). To manage emissions in project construction, TenneT has used hydrogen-based drilling systems and electrically driven rigs for tunnel systems.

TenneT’s Dutch investment project portfolio will steadily expand as projects marked in the planning stages gradually reach financial closures. With pressure on timeliness, more initiatives in technology and processes are likely.

Outlook

TenneT plans to construct 2,500 km of new grid connections in the Netherlands by 2045, both on land and at sea (TenneT, 2024). The operator’s long-term goals are aligned with the policy objectives in decarbonisation. It is, however, the short to medium-term horizon which attracts attention. The country’s exponential rise in the renewable power project pipeline has outstripped grid capacity growth in several pockets of the network. Added pressure also comes from the need to strengthen the existing grid assets rapidly.

With rising grid demands, grid expansion project delays may have bigger ramifications than in the past. TenneT’s observations, placed in the transmission planning documents of 2024, show that out of the 252 grid projects already in planning stages, 60 were delayed due to both internal and external factors. The grid connection requests, meanwhile, continue to pile up. TenneT’s half-year report of 2024 outlined this challenge – pending connection requests rose from about 45 in 2019 to over 700 in the Netherlands by July 2024. Among other factors, the company must circumvent material and resource constraints, including skilled personnel, construction inputs, or dependencies between projects, which collectively impact the scope and execution (TenneT, 2024).